|
A Brief History
The original sewage Treatment Plant for the area was built in Olympia by the City to meet its own wastewater needs. Construction of the Plant was authorized by the City Commission
in 1949 and primary treatment went on-line in the early 1950s. The City of Tumwater and the Olympia Brewing Company contracted
with Olympia for wastewater treatment service in 1954 and were
both connected to the system in 1955. Later, in 1969, Lacey also
contracted with Olympia for service and connected to the system.
To qualify for state and federal grants, an Interlocal
Agreement between the three cities and the county was signed in
1976. It provided for cooperative use and development of the
Olympia Treatment Plant, established jointly funded major sewer
lines and initiated an intergovernmental planning process for a
major upgrade of the Treatment Plant. The resulting 1983 upgrade
provided secondary treatment of wastewater.
The treatment plant was further upgraded in the early 1990s
to add nitrogen removal and ultraviolet disinfection and upgrade
the plant's outfall into Budd Inlet. Those new systems came
on-line in 1994.
As the result of a major Inflow and Infiltration study
conducted from 1992-1994, the LOTT Partners learned their
Treatment Plant could reach capacity as soon as 2001 during wet
weather. In September 1995, they began a four-year long-range
planning process, resulting in the Wastewater Resource
Management Plan. A new Intergovernmental Agreement was approved
by the four LOTT Partners in January 2000 to restructure LOTT
and implement the Plan.
In 2004, the first upgrade under the new Plan occurred at the
Budd Inlet Treatment Plant, with the addition of a new Class A
Reclaimed Water sand filter system. The same year, construction
began on LOTT's first satellite facilities the Martin Way Reclaimed Water
Plant, constructed Wetland Ponds, and Groundwater
Recharge Basins that make up the Hawks Prairie Reclaimed Water
Satellite. The Satellite became operational in 2006; testing and fine tuning followed.
Organization and Governance Structure
The original 1976 LOTT governance structure was a partnership on
paper. LOTT did not exist as an entity. The City of Olympia was
the legal owner of all LOTT facilities, and operated them on
behalf of all four partners. The City of Olympia also held all
financial responsibility and contract authority for the
partnership. While LOTT operations were guided by an elected
official from each of the four Partner governments, known as
"The Advisory Committee" (TAC), they were technically advisory to
the Olympia City Council.
As a result of the 1995-1999
long-range planning process, the new LOTT Wastewater Alliance
was incorporated as a non-profit organization on April 17, 2000.
A transitional period followed, during which legal documents
were prepared for transition of LOTT assets, financial
authority, and outstanding agreements from the City of Olympia
to the new organization. The transfers were completed effective
July 1, 2001, and LOTT became a full stand-alone entity for the
first time.
Initially, operation and maintenance of the LOTT facilities
stayed with Olympia, under contract to the LOTT Alliance.
Effective January 1, 2005, LOTT assumed full responsibility for
those services as well.
The LOTT Alliance is governed by a Board of Directors. Four
elected officials one from each of the partner governments
are appointed to represent their jurisdictions on the Board. The
Board provides policy oversight for planning, construction,
financing, and operations of LOTT programs and joint facilities
and plans for future facilities.
Public Values
LOTT's long-range planning was guided by a series of 10
Public Values, identified as the result of public opinion
surveying at the beginning of the planning process. Those public
values continue to guide planning and implementation of LOTT's
programs and capital projects.
- As a first priority, maximize utilization of LOTT's
existing treatment capacity. Manage demand to avoid or
delay the need for new treatment capacity.
- Prepare a plan that meets current and future
wastewater needs throughout the LOTT service area.
Accommodate planned growth, consistent with LOTT's legal
requirements.
- Select wastewater facilities for the region's future
that yield maximum benefits to the environment.
Mitigate any potentially adverse impacts of new facilities.
- Take all possible steps to control facilities costs.
Carefully consider the lowest cost and most cost-effective
alternatives, and evaluate the impact on LOTT ratepayers.
- Treasure LOTT's treated wastewater as a valuable,
long-term resource to be cleaned and restored, reused,
then ultimately returned to the environment.
- Clearly define, demonstrate and document the value to
the community of new facilities needed for the future.
Design any new LOTT facilities to produce multiple
benefits for the community.
- Conduct a pro-active and open facilities planning
process that informs and involves citizens in planning
and decision making.
- Assure an equitable distribution of costs for any
new facilities between current ratepayers and new
development.
- Establish an organizational structure to build and
operate the region's future facilities effectively and
efficiently, and that assures equitable and accountable
representation of the public.
- Integrate LOTT's facilities plan with other related
local issues, plans and infrastructure programs to
maximize regional cooperation and avoid duplication of
effort and cost.
|